The road construction team have started work on Morlais now with an estimated completion time of 4 - 5 weeks. Work has now finished on all the villa structures & pools. The tiling teams estimate is 3 - 4 weeks to complete all the swimming pools & villas. Central heating systems are now being installed and the painting team is moving from villa to villa. The stone walling is almost complete on site, maybe 2 weeks will see everything finalised. Over the coming week all the residents on Morlais will receive a handover document via email to let you know the process of taking possession of your villa. If anyone wishes to have more information please contact our Admin or Sales team.
Plot 8 is still for sale with a completion date in September - for more information please contact Bryn at sales@carringtoncyprus.com
|